La información de esta página es para clientes en 

{{ nombre del pueblo }}

Winter Construction Moratorium

Eversource has a construction moratorium effective December 1 to April 15. This affects all underground sub developments (subdivisions), underground service changes and underground service relocations.

If you have pending jobs of these types, all prerequisites (contribution, easement, inspection, etc.) need to be completed by November 1. At that time, we will make every effort to schedule or start the work within three weeks, depending on the scope and weather.

Reminder: When submitting a request for sub developments, we require an 8-week notice and approved town or city plans.